Diario de Obras · Wed 18 Nov
Site report · Sant Josep de sa Talaia, Ibiza

Can Leela

Wednesday, 18 November 20265 workers42.5 hSunny · 19°C
Dressing marès stone for the north terrace wallIllustrative
In brief
  • North terrace stone wall: 14 linear metres raised to final height.
  • Perimeter drainage: 22 m of slotted pipe laid along the west façade.
  • Main bedroom electrical conduits completed.
  • Marès stone delivery confirmed for Friday.
Alerts & actions
  • Schedule the conduit inspection before Monday.
  • Rain forecast on Thursday: cover the open trench.
Site report

Work on the north terrace continued with the dry-stone retaining wall that will support the new olive terrace. Rubén Costa and Iván Torres dressed and set the local marès stone along the central section, raising fourteen linear metres to the final height of 1.20 m agreed with the architect. Each stone is selected and dressed on site so that its face matches the existing walls of the finca, which is why the wall advances section by section rather than in one continuous run.

Along the west façade of the house, Abdel Benali and Marius Popescu completed twenty-two metres of the perimeter drainage. The trench was lined with geotextile, filled with a gravel bed, and the slotted pipe was laid with a continuous fall towards the existing soakaway. This drainage protects the restored foundations from the damp that had affected the west wall before the works began.

Inside, Pau Cardona finished the conduits and junction boxes in the main bedroom, following the revised lighting layout approved last week. The room is now ready for the conduit inspection before lime plastering can begin. At the end of the day the terrace and access path were cleaned, and the remaining stone was stacked and covered.

Gallery

Images are illustrative placeholders, not real project evidence.

Work completed
  • 14 m of dry-stone wall on the north terrace
  • 22 m of perimeter drainage along the west façade
  • Conduits and boxes in the main bedroom
  • Terrace and access cleaned
Outstanding tasks
  • Final 9 m of the north wall
  • Connect drainage to the soakaway
  • Bedroom conduit inspection
Upcoming activities
  • Fri 20 Nov · Delivery of 6 pallets of marès stone
  • Mon 23 Nov · Lime plaster starts in the main bedroom
  • Tue 24 Nov · Site visit by architect Laia Ribas
Crew
  • Rubén CostaStonemason
  • Iván TorresStonemason
  • Abdel BenaliLabourer
  • Marius PopescuBricklayer
  • Pau CardonaElectrician

Based only on confirmed site facts. Consolidated from 5 individual worker submissions. In production, AI drafts this text from confirmed facts; the supervisor reviews it before publishing.