Can Leela's stone wall advances as materials arrive at Gina
2
Active sites
9
Workers involved
10
Photos & videos
In brief
Can Leela: 14 m of stone wall and 22 m of drainage completed.
Gina: materials received and first-floor formwork at 60%.
Rain forecast Thursday: protect trenches and formwork.
Published read-only snapshot · v1
01 · Sant Josep de sa Talaia
Can Leela
5 workers 42.5 h
Illustrative
Illustrative
Illustrative
0:48
Illustrative
Illustrative
Achievements
North terrace stone wall: 14 linear metres raised to final height.
Perimeter drainage: 22 m of slotted pipe laid along the west façade.
Main bedroom electrical conduits completed.
Marès stone delivery confirmed for Friday.
Work on the north terrace continued with the dry-stone retaining wall that will support the new olive terrace. Rubén Costa and Iván Torres dressed and set the local marès stone along the central section, raising fourteen linear metres to the final height of 1.20 m agreed with the architect. Each stone is selected and dressed on site so that its face matches the existing walls of the finca, which is why the wall advances section by section rather than in one continuous run.
Outstanding tasks
Final 9 m of the north wall
Connect drainage to the soakaway
Bedroom conduit inspection
Upcoming activities
Fri 20 Nov · Delivery of 6 pallets of marès stone
Mon 23 Nov · Lime plaster starts in the main bedroom
6 pallets of stone paving and 40 bags of cement received and stored.
First-floor water and drainage set-out completed.
Formwork to the north edge of the first-floor slab 60% complete.
Upper terrace cleaned and materials protected.
The day began with a material delivery coordinated by Toni Planells. Six pallets of stone paving and forty bags of cement were unloaded by crane truck and stored on the lower platform, away from the pool area, so that they would not obstruct the formwork on the upper level.
In production, each edition is drafted by AI from individual worker submissions, reviewed by the supervisor and published as a read-only snapshot. This edition is written demonstration content.
Images are illustrative placeholders, not real project evidence.