01 · Sant Josep de sa Talaia
Can Leela
5 workers
42.5 h
42.5 h
Illustrative
IllustrativeAchievements
- North wall: 8 linear metres set.
- West façade drainage trench excavated (22 m).
- Main bedroom conduits 60% complete.
The stonemasonry team advanced eight metres of the north wall, starting at the eastern end where the ground requires a wider base. In parallel, the west façade drainage trench was excavated by hand to avoid damaging the roots of the century-old olive tree beside the house.
Outstanding tasks
- Lay geotextile and gravel in trench
Upcoming activities
- Wed 18 Nov · Drainage pipe and wall continues