Site report · Santa Eulària des Riu, Ibiza
Gina
Tuesday, 17 November 20264 workers34 hCloudy · 17°C
IllustrativeIn brief
- Pool shell waterproofing inspected and accepted.
- First-floor slab formwork started.
Site report
The pool shell watertightness test was completed after 72 hours of filling with no measurable loss, so the waterproofing was accepted. This freed the lower platform for use as a storage area.
Andrei Ionescu and Luuk de Vries began the first-floor slab formwork from the south side, while Sergio Tur checked the ground-floor drainage stubs.
Gallery
Images are illustrative placeholders, not real project evidence.
Work completed
- Pool watertightness test
Outstanding tasks
- North-edge formwork
Upcoming activities
- Wed 18 Nov · Paving and cement delivery
Crew
- Sergio TurPlumber
- Andrei IonescuBricklayer
- Youssef AmraniLabourer
- Luuk de VriesCarpenter
Based only on confirmed site facts. Consolidated from 4 individual worker submissions. In production, AI drafts this text from confirmed facts; the supervisor reviews it before publishing.