Site report · Santa Eulària des Riu, Ibiza
Gina
Monday, 16 November 20264 workers34 hSunny · 20°C
IllustrativeIn brief
- South façade scaffold raised to the new level.
- Temporary power supply extended.
Site report
The south façade scaffold was raised to first-floor level and perimeter edge protection was extended before formwork began.
Sergio Tur extended the temporary power supply with a new site distribution board on the first floor.
Gallery
Images are illustrative placeholders, not real project evidence.
Work completed
- South scaffold raised
Upcoming activities
- Tue 17 Nov · Pool watertightness test
Crew
- Sergio TurPlumber
- Andrei IonescuBricklayer
- Youssef AmraniLabourer
- Luuk de VriesCarpenter
Based only on confirmed site facts. Consolidated from 4 individual worker submissions. In production, AI drafts this text from confirmed facts; the supervisor reviews it before publishing.