- North wall: 8 linear metres set.
- West façade drainage trench excavated (22 m).
- Main bedroom conduits 60% complete.
The stonemasonry team advanced eight metres of the north wall, starting at the eastern end where the ground requires a wider base. In parallel, the west façade drainage trench was excavated by hand to avoid damaging the roots of the century-old olive tree beside the house.
Inside, Pau Cardona began the main bedroom conduits following the new lighting layout. Marius Popescu repaired two timber lintels in the east wing corridor.
- 8 m of north wall
- West trench hand-excavated
- Two lintels repaired
- Lay geotextile and gravel in trench
- Wed 18 Nov · Drainage pipe and wall continues