Tuesday, 17 November 2026PublishedVersion 1Reviewed by Javier Marí
Workers
4Hours
34Weather
Cloudy · 17°CExecutive summary
- Pool shell waterproofing inspected and accepted.
- First-floor slab formwork started.
Detailed report
The pool shell watertightness test was completed after 72 hours of filling with no measurable loss, so the waterproofing was accepted. This freed the lower platform for use as a storage area.
Andrei Ionescu and Luuk de Vries began the first-floor slab formwork from the south side, while Sergio Tur checked the ground-floor drainage stubs.
Work completed
- Pool watertightness test
Outstanding tasks
- North-edge formwork
Upcoming activities
- Wed 18 Nov · Paving and cement delivery