Gina, floor slabs and pool structureIllustrative
FES-25-004 · Santa Eulària des Riu, Ibiza

Gina

Gina — Vivienda unifamiliar de obra nueva

Construction of a 340 m² two-storey home, infinity pool, terraces and external landscaping.

In progress
38%
Current phase
Structure and first-floor services
Client
Famille Laurent
Supervisor
Javier Marí
Project manager
Daniel Ferrer
Architect
Laia Ribas
Start
18 May 2026
Planned completion
30 September 2027

Daily reports3

Tuesday, 17 November 2026PublishedVersion 1Reviewed by Javier Marí
Workers
4
Hours
34
Weather
Cloudy · 17°C
Executive summary
  • Pool shell waterproofing inspected and accepted.
  • First-floor slab formwork started.
Detailed report

The pool shell watertightness test was completed after 72 hours of filling with no measurable loss, so the waterproofing was accepted. This freed the lower platform for use as a storage area.

Andrei Ionescu and Luuk de Vries began the first-floor slab formwork from the south side, while Sergio Tur checked the ground-floor drainage stubs.

Work completed
  • Pool watertightness test
Outstanding tasks
  • North-edge formwork
Upcoming activities
  • Wed 18 Nov · Paving and cement delivery
Gallery

Images are illustrative placeholders, not real project evidence.

Consolidated from 4 individual worker submissions. In production, AI drafts this text from confirmed facts; the supervisor reviews it before publishing.